Norfolk County Making Strides in Achieving Long Term Financial and Infrastructure Sustainability

Ontario, Canada
Overview

The Corporation of Norfolk County (Norfolk) worked with Echologics® to critically assess 6.9 kilometers  (4.3 miles) of a critical ductile iron water transmission main in order to address four primary objectives: determine the existing structural condition of the ductile iron main, investigate the main for the existence of any leaks, develop budgetary estimates of replacement and lining rehabilitation, provide recommendations of the preferred pipeline renewal options if needed.

To achieve these objectives, Echologics utilized its patented ePulse® condition assessment technology. In addition, Echologics engaged AECOM to provide pipeline renewal options.

4.3 miles
Ductile iron transmission main tested
12 of 54
segments assessed as poor condition
1
Point of Interest Identified

Situation

Norfolk County, a municipality in Ontario, Canada, was incorporated as a city in 2001 and has a population of more than 60,000 residents. Norfolk is located 56km (35miles) southwest of Hamilton and 97km (60miles) southeast of London.

The county encountered a main break on its 12˝ ductile iron transmission water main which is the only feed from the community of Port Rowan to the community of St. Williams, so the impact to residents was significant. The team suspected that the leak on this line was caused by pitting corrosion, a common cause of failure in ductile iron pipes. During the repair, the Water Operations staff noted that there was significant deterioration and corrosion to the bottom section of the ductile iron water main.

“Norfolk County has other communities that are fed from well sites via these transmission mains. These sites are also vulnerable because of the single feed and lack of redundancy,” shared Jeff Demeulemeester, CET, Project Manager – for Norfolk County.

Norfolk’s 10-year Capital Plan, an integral component of its long-term financial sustainability program, underscored the importance of ensuring projects are prioritized, substantiated, and affordable.

Solution

For Norfolk, it was imperative to understand the existing conditions of its water mains to ensure effective preventative maintenance. To do so, a Request for Proposal for a condition assessment using nondestructive technology was issued. After rounds of trials and deliberation, Echologics® ePulse® non-invasive condition assessment technology by Mueller was selected to determine the existing structural condition and locate any existing leaks and anomalies.

For this project, Echologics tested approximately 6.9km (4.3miles) of the ductile iron transmission main running primarily along Front Road. Norfolk selected this section of pipe due to its lack of redundancy and previous break history. Since a failure on this line could also have a large impact on Norfolk’s residents, a condition assessment survey was performed to determine if any areas along the line had experienced significant degradation. Based on the findings, the engineering firm, AECOM, would recommend the next steps of pipeline renewal options, if needed.

ePulse® technology was implemented by attaching two acoustic sensors, each to an existing contact point, such as a fire hydrant, valve, or directly in contact with the pipe wall. A sound wave was induced in the pipeline and its propagation speed was measured between the two acoustic sensors.

The speed at which the sound wave traveled was dictated by the condition of the pipe wall. After fieldwork is completed, the speed of sound is combined with other information collected on site, including distance and water temperature, and then using proprietary advanced algorithms, the technology is able to determine the average wall thickness remaining for each segment. These results were interpreted in the form of three categories, “good”, “moderate”, and “poor”. A wall loss percentage that was less than 10%, was denoted as good; a wall loss percentage from 10% to 30% was denoted as moderate; a percentage that was larger than 30% was classified as “poor”.

“Each ePulse® result represented an average condition within a segment between two sensor attachment points. Often, when planning a replacement program, asset managers are looking for an overall score representative of pipe condition to rank pipe for replacement. ePulse® results are great for this purpose” said Khalid Kaddoura, Project Manager – for AECOM.

The second part of the project required an investigation for leaks and anomalies, which was simultaneously fulfilled during the condition assessment. This is the advantage of deploying ePulse® as both assessment and leak detection could be performed at the same time with the same acoustic correlator.

Results

After a 12-day assessment period, ePulse® results indicated that 12 of the 54 segments were in poor condition with an average wall thickness loss greater than 30%. 30 segments appeared to be in moderate condition with 10% to 30% loss in original wall thickness. 11 segments appeared to be in good condition with less than a 10% loss in original wall thickness, and the remaining one segment could not be assigned a result.

No leaks were detected during the time of the survey. However, a point of interest (POI) was identified. POI designation indicated that some, but not all of the criteria for a positive leak detection result were met. A secondary investigation later confirmed that the leak noise originated from a normal functioning pressure reducing valve within a meter pit.

“We are pleased that the project provided the data we required to prioritize and make an educated schedule for replacement based on the watermain’s remaining wall thickness. Furthermore, the cost of the assessment was considered minor as it provided Norfolk County with the required data to prioritize the replacement of our transmission main network over the 10-year Capital Plan. Based on a ‘worst first’ replacement schedule, we were able to align the timing with our required financial planning,” said Jeff.

Based on the results collected by the Echologics field team, AECOM developed a customized renewal decision tree along with budgetary cost estimates of some renewal options. Incorporating ePulse® inspection results, the decision tree was based on the three condition categories: good, moderate, and poor.

For the first two categories of good and moderate, the watermain's hydraulic performance was recommended to be assessed. If it fell within the acceptable range, an additional assessment would be performed to check the water characteristics. A rehabilitation intervention was recommended if the water quality did not comply with the local standards. On the other hand, if the watermain’s hydraulic performance was unacceptable and/or was determined to be in the poor condition category, a replacement was recommended should a larger hydraulic capacity be required. If the hydraulic capacity was sufficient, renewal techniques were considered on a case by case basis, depending on cost and construction footprint analysis

Following the project completion, Norfolk County scheduled the replacement of pipe sections in poor condition, with more sections identified to be replaced in its 10-year Capital Plan. The results of the Norfolk ePulse® readings were further utilized as research presented in the Canadian Society for Civil Engineering (CSCE) Annual Conference and published in the conference’s proceedings.

Related Resources